• +250 788 572 696
  • +250 788 304 329
  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Projects

When: 2017

Project status: Completed

Project description: ALTES has been engaged on assignments by UOB to provide for services of design and construction of their new Disaster Recovery Data Center in MUHANGA including a raised floor and relocation of their IT infrastructure from their old DR Site to the newly completed DR Site.

Deliverables:

  • Electrical and structured cabling installations, data center equipments relocation from Kigali and reinstallation, air-conditioning complete with raised floor.

When: 2019 up to now

Status: ongoing

Project Description: Maintenance services data center

Deliverables:

  • Data center maintenance services for BPR DATA CENTER in MUHIMA and DISASTER RECOVERY SITE in RUHANGO this cover periodical maintenance and support their 4 cooling APC INROW cooling units and 160KVA SYMETRA-PX APC UPS in MUHIMA and 2 cooling APC INROW cooling units and 30KVA SUVT APC UPS in RUHANGO DR.

When: 2020-2021

Status: Completed

Project description: Periodical maintenance and services of on duty generator for their Disaster Recovery site in BUGESERA.

When: 2020

Status: Completed

Project description: ALTES provided this international Feeds Mill and trader with installation servirces of their refrigirated container.

Deliverables:

  • Supply and installation of various electrical materials to supply power to the reefrigirated container complete with its metering system.

When: 2020

Status: Completed

Project description: ALTES has been engaged on assignments by UB to providing services of revamping and fitting to the new architectural designs of electrical and structured cabling installations for their HEAD quorters office,Remera branch,Kimironko branch and KCM branch.

Deliverables: 

  • Electrical and structured cabling installations, and air-condi- tioning.

When: 2017

Status: Completed

Project description: Supply and installation of 50Kva AVR plus construction and connection of a low voltage commercial power line to the same site.

Deliverables:

Supply and installation of 50Kva AVR complete with the construction and connection of a low voltage commercial power line at Rubengera core site.

When: 2019 - 2022

Status: Completed

Project description: Facility maintenance services

Deliverables:

  • Mechanical, electrical & plumbing maintenance services for the whole campus complete with follow up on water purification system and the 15KW submersible water pumping system

When: 2017

Status: Completed

Project description: Supply and installation of data center cooling units

Deliverables:

  • heavy duty air conditioning system for core site data center LOT2

GiSAGARA DISTRICT

When: 2019-2020

Status: Completed

Project description: Construction of 6 Km of public lighting

Deliverables:

  • Construction of 6Km of public lighting in 3 different business centers in Gisagara District.

When: 2017

Status: Completed

Project description: Supply and installation of slave & master generators 2x50Kva an 2x80Kva

Deliverables:

Supply and installation of slave & master generators with extra 2000 liter fuel tank 2x50Kva and 2x80Kva for Huye core site and Rubengera core site.

Phone